Nuremberg harbour, temporary bridges

  • Structural engineering
  • Road and traffic route construction
  • Civil engineering
  • Eiffage Infra-Süd

Kund

Stadt Nürnberg Servicebetrieb Öffentlicher Raum (SÖR)

Projektvolym

11.000.000 €

Byggtid

52 months

Two steel bridges over the Main-Danube Canal and south-west bypass as temporary bridges during the construction of the new Nuremberg harbour bridges

Construction of two steel bridges over the Main-Danube Canal and the A 73 / South-West Bypass:

  • Construction of the temporary bridges whilst the new Nuremberg harbour bridges are being built
  • followed by the dismantling of the temporary bridges upon completion of the entire construction project