House Aden 1st construction phase

  • Civil engineering
  • Specialised civil engineering
  • Eiffage Infra-Nordwest
  • Eiffage Infra-Spezialtiefbau

Kund

RAG Aktiengesellschaft

Projektvolym

39.500.000 €

Byggtid

08.2021  –  04.2026

Reorganisation of central water drainage Haus Aden 1st construction phase

Reorganisation of the central drainage system at Haus Aden – Phase 1.

  • Two bored pile excavation pits for pipe jacking to a depth of 20 m
  • 1,500 m of DA 508 steel pressure pipeline
  • 3,000 m of DA 1016 steel pressure pipeline
  • 800 m of DN 600 cast iron pressure pipeline
  • 825 m of leak-monitored PE-HD lining, DA 710
  • 4 in-situ concrete shaft structures
  • Steel structures for the utility duct and manholes