New bridge construction and roadworks for the relocation of the B173 between Lichtenfels and Hochstadt, BW 11-2

  • Structural engineering
  • Road and traffic route construction
  • Civil engineering
  • Eiffage Infra-Süd

Kund

Staatliches Bauamt Bamberg

Projektvolym

54.000.000 €

Byggtid

44 months

New construction of bridge BW 11-2 over the Main and the Bamberg-Hof railway line:
The structure consists of seven spans and is being built using the steel composite construction method with incremental launching.

Construction of the new BW 11-2 bridge over the Main and the Bamberg–Hof railway line:

  • Structure comprising seven spans
  • Constructed using a composite steel structure
  • Segmental sliding method