Dülmen southern bypass

  • Structural engineering
  • Eiffage Infra-West

Kund

Deutsche Bahn Netz AG, Hamm

Projektvolym

1.36 million EUR

Byggtid

October 2015 - September 2016

Construction of a new railway overpass at Dernekämper Höhenweg on the line between Dülmen and Sythen

Work under partial and full closure
Full closure for the bridge insertion (04 - 09/05/2016)

  • Removal of track yokes and superstructure
  • Shoring the superstructure
  • Installation of transverse shoring to secure masts
  • Re-anchoring of cross shoring
  • Construction of the excavation pit, shunting track
  • Insertion of the frame weighing more than 2500 tonnes over a distance of 45 m
  • Backfilling of the frame
  • Removal of shoring and anchoring
  • Restoring the superstructure and tracks
  • Dismantling of auxiliary cable bridges and cable re-laying in cable duct final position