Work under partial and full closure
Full closure for the bridge insertion (04 - 09/05/2016)
- Removal of track yokes and superstructure
- Shoring the superstructure
- Installation of transverse shoring to secure masts
- Re-anchoring of cross shoring
- Construction of the excavation pit, shunting track
- Insertion of the frame weighing more than 2500 tonnes over a distance of 45 m
- Backfilling of the frame
- Removal of shoring and anchoring
- Restoring the superstructure and tracks
- Dismantling of auxiliary cable bridges and cable re-laying in cable duct final position