Southern bypass B 58n Wesel

  • Structural engineering
  • Civil engineering
  • Eiffage Infra-West

Kund

Straßen.NRW

Projektvolym

35.2 million EUR

Byggtid

June 2020 - October 2022

Eiffage Infra-West has been involved in the B 58n Wesel southern bypass project since September 2019.

It began with the contract to relocate the pipeline and bypass the B8 (project volume €6.6 million), followed by the commissioning of Eiffage Infra-West and Eiffage Infra-Spezialtiefbau for the second sub-project to construct the bored pile wall (project volume €5.75 million). We were also able to secure a further sub-project.

Straßen.NRW commissioned Eiffage Infra-West together with Eiffage Infra-Spezialtiefbau for the next project with earthworks, embankment construction, drainage and road construction, sealing and diaphragm wall construction as well as engineering structures (BW 2+3) and track construction.

This cross-company contract requires the construction expertise of all parties involved. "The task now is to jointly develop a complex workflow in which one gear meshes with another. With the combined expertise from our companies, I am sure that we are ideally equipped for this task as a well-coordinated team," explains Roger Nebelo, Head of Civil Engineering/Industrial Construction at Eiffage Infra-West.

The project volume for the new project is €35.2 million. It runs from 29 June 2020 to 21 October 2022.

On 9 July 2021, the 10,000-tonne bridge structure was moved to its destination. The structure was erected as a whole next to the railway line and moved to its planned location using a hydraulic system via a 70-metre-long skidway. The bridge is 69 metres long, 23 metres wide and almost 10 metres high and carries the railway line over the B58n.

Further information can be found at straßen.nrw.de:
B58n new construction of the Wesel bypass | Straßen.NRW