New railway overpass
- Clear width of 6.00 m
- Clearance height of >= 4.25 m
- Production of reinforced concrete half frame in FT construction method,
4 parts substructures + 2 caps and 2 foundation beams in field factory
- Construction of an auxiliary cable bridge for railway cables
- Total track closure, section 2250
- Demolition: Demolition of existing structure and construction of excavation pits
- Lifting in the prefabricated parts and applying internal prestressing
- Backfilling of the excavation pits, restoration of the tracks incl. LST work