Track renewal on Allersberger Straße in Nuremberg

  • Track and railway construction
  • Eiffage Infra-Süd
  • Project update

Projektvolym

1.960.000 €

Byggtid

05.2026  –  05.2027

Nuremberg Tramway, Allersberger Straße Track Renewal, Lot 1: Slab Track

  • Renewal of the track system, including dismantling and laying of new track over a length of approximately 500 metres
  • Lot 1: a total of approx. 700 metres of track as ballasted track
  • Refurbishment in-situ
  • Route optimisation with minimal track realignment
  • Photos © VAG Nuremberg