Herrenstraße level crossing (length approx. 9 m, clear width 6 m)
- Ground stabilisation using HDI
- Production of reinforced concrete half-frame in FT construction method, 7 parts substructures + 2 caps in field factory
- Construction of an auxiliary cable bridge for railway cables
- Total closure of line 3010 Koblenz-Perl from 27/10/2017 to 02/11/2017
- Dismantling track systems and securing overhead line mast
- Demolition of existing structure and construction of excavation pits
- Lifting in the prefabricated parts and applying internal prestressing
- Backfilling of the excavation pits, restoration of the tracks incl. LST work
St. Georgstraße level crossing (length approx. 18 m, clear width 3 m)
- Construction of reinforced concrete half frame and wing extension in FT construction method,
- 12 parts of substructures + 1 cap in field factory
- Construction of an auxiliary cable bridge for railway cables
- Total closure of line 3010 Koblenz-Perl from 27/10/2017 to 02/11/2017
- Dismantling of track systems incl. 2 points
- Demolition of the existing structure and construction of the excavation pits
- Lifting in the prefabricated parts and applying internal prestressing
- Backfilling of the excavation pits, restoration of the tracks incl. LST work