Hegebach, Hilgenbach, Werderstraße in Oer-Erkenschwick
Sewer construction
DN 500/DN 600 FBS concrete pipes and approx. 80 metres of DN 1000 FBS concrete pipes were laid over a length of approx. 600 metres. Precast concrete manhole structures and special manhole structures were relocated.
Flood retention basin and the drainage
- approx. 3,600 m³ installation of topsoil
- approx. 23,500 m³ of excavated soil from the RRB base & drain, landfill to AN
- approx. 6,800 m² additional topsoil removal in the HRB area
- Rock fill from armourstone
- Wet seeding
- Construction of a new throttle structure (equipment and technical installation)
- Fence and gate installations
- Earthworks for the relocation of a DN 350 GG water pipe