Construction of two new sidings towards Mecklenheidestraße, which were connected to the existing track layout via four new points. As part of this work, existing track layout was also dismantled and modified.
This included the following works:
- 10,500 tonnes of soil, old ballast and construction waste excavated and disposed of
- 900 tonnes of soil excavated and reinstated
- 2,420 tonnes of PSS supplied and installed
- 300 m of deep drainage supplied and installed
- 235 m of track removed
- 900 m of track laid
- 4 sets of points supplied and installed
- 1,050 m of rail supplied
- 770 sleepers supplied
- 3,070 tonnes of ballast supplied
- 7 lighting units with masts supplied and installed
- 7 driven-pipe foundations constructed