Tram Nuremberg, Walzwerkstraße to Ostbahnhof

  • Track and railway construction
  • Eiffage Infra-Süd
  • Project update

Kund

VAG Verkehrs-Aktiengesellschaft Nürnberg

Projektvolym

EUR 1.7 million net

Byggtid

August - November 2025

Nuremberg tramway

Renovation of 475 metres of double track in Äußere Sulzbacher Straße, between Walzwerkstraße and Ostbahnhof

  • Demolition and removal of existing tracks with different superstructure systems - the existing tracks were installed as ballastless track with mastic asphalt, in some cases even underpouring was used.
  • Installation of tracks of the "Slab track 2016 with grooved rails 59R2 with special grade concrete" superstructure system
  • Route optimisation