Renovation of the double-track tram line in Nuremberg, Walzwerkstraße

  • Track and railway construction
  • Eiffage Infra-Süd
  • Project update

Client

VAG Verkehrs-Aktiengesellschaft Nürnberg

Project volume

1.700.000 €

Construction time

08.2025  –  11.2025

Nuremberg Tramway: Refurbishment of 475 m of double track on Äußere Sulzbacher Straße, between Walzwerkstraße and Ostbahnhof

  • Demolition and removal of existing tracks with various track-bed systems – the existing tracks were laid as a rigid track bed with mastic asphalt; in some sections, underlay was even used.
  • Installation of tracks using the “Feste Fahrbahn 2016” track system with 59R2 grooved rails and special-grade concrete
  • Route optimisation