The plant was constructed in several stages:
- Preparatory measures
- Sheet pile sealing wall constructed and maintained until the end of the construction project. 3,700 m² of steel sheet piling in lengths between 14.0 and 15.0 metres was installed as a temporary sealing wall.
- Construction of a sheet piling box using the CSM (Cutter-Soil-Mix) method. The soil was excavated underwater, after which 950 m³ of underwater concrete was placed as the base of the excavation pit.
- Construction dewatering
- Closed dewatering with vertical filter wells, combined with vacuum filter lances including water treatment for transfer to the tunnel stream; geodetic head up to 6.0 metres.
- Civil engineering, engineering and traffic facilities
- Neutralisation basin facility with a basin volume of up to 3,600 m³.
- Traffic facilities in asphalt construction including drainage and lighting
- Mechanical and process engineering including pipeline construction and steel construction for
- Feed
- Neutralisation / sedimentation / post-sedimentation
- Demangling / final pH adjustment
- Dewatering
- Control air supply / drinking and process water supply
- Exhaust air technology and unloading area for chemicals
- Electrical and process control technology
- Ensuring the security of supply of the existing plant
- Utilisation and expansion of the existing infrastructure
- Medium-voltage supply / central main energy management / decentralised low-voltage supply
- Automation and process control technology focussing on
- Social building
- Sludge treatment
- Chemical treatment
- Lime milk treatment
- Communication technology