Berne middle course

  • Civil engineering
  • Eiffage Infra-Nordwest
  • Eiffage Infra-Spezialtiefbau

Kund

Emschergenossenschaft Essen

Projektvolym

105 million €

Byggtid

07/2020 - 05/2025

Construction of sewers and rainwater treatment plants in Essen

ARGE partner EI-ST:

  • 2 overlapped bored pile construction pits, D=12 and 15 m; D=14 m
  • 1,600 m tunnelling as a partial cut with compressed air from DN 2000 (OD 2400) to DN 3800 (OD 4700) with reinforced concrete pipes
  • Diaphragm wall excavation D=1.20 m lamella thickness; 100 m long; 8 m wide and 36 m lamella embedment, 18 m of which in marl

ARGE partner Smet Tunnelling:

  • 1600 m AVN tunnelling from DN 1200 (OD 1560) to DN 2800 (OD 3600) with reinforced concrete pipes
  • 246 m microtunnelling from DN 300 to DN 800

EI-NW:

  • 7 excavation pits in CSM construction with diameters of up to 10 m and lamella lengths of up to 19 m; excavation to a depth of 16 m
  • Sinking of 8 lowering shafts up to 3.60 m in diameter with UW concrete bases
  • Excavation of the SKU to a depth of 18 m
  • Installation of double-layer excavation reinforcements up to HEM 1000
  • Sheet piling work to secure the embankment
  • Filling of excavation pits, partly with liquid soil mixed in-house
  • Construction of prefabricated shafts, surfaces, earthworks, stream pipework, open installations, entry and exit sluices for the tunnelling work
  • 13,600 m³ of reinforced concrete construction for structures on our own and with NU
  • Disposal of 300,000 m³ of excavated soil from excavation pits and drives
  • Construction and connection of 4 DN 1000 inspection shafts; T=up to 14 m to the tunnels