No sign of demolition...

  • Structural engineering
  • Road and traffic route construction
  • Civil engineering
  • Eiffage Infra-Süd
  • Project update
  • Company news

A week after the bridge was demolished , our Flembach Bridge in Michelfeld is already looking noticeably ‘tidier’. There’s no sign left of the massive concrete sections or the piles of earth. Quite the opposite, in fact – work on the new structure is already well under way👏: All the bored piles have been installed and the base courses have been concreted. Today, Friday 14 August 2026, the bored piles are being trimmed, and from Monday 17 August 2026, formwork work on the abutmentswill begin💪.

As we had already suspected last week, our construction site in the Flembach Valley is unrecognisable after just one week’s work . See for yourselves and be amazed💫!

We wish you continued success, plenty of energy and good luck for the coming weeks, as well as an accident-free construction period🍀! We’re already looking forward to the end of the next week of road closures.