Temporary diversion for the replacement construction of the bridges at Nuremberg Harbour

  • Structural engineering
  • Road and traffic route construction
  • Civil engineering
  • Eiffage Infra-Süd
  • Project update

Client

Stadt Nürnberg

Project volume

10.000.000 €

Construction time

03.2025  –  03.2026

Nuremberg, construction of the temporary bypass for the replacement bridges over the Main-Danube Canal and the South-West Bypass

  • 700 m temporary bypass
  • 40,000 m³ of earthworks; sheet pile wall shoring
  • 105 m of solid retaining wall
  • 10,000 m² of asphalt surfaces
  • 1,000 m of concrete drainage pipes

Redesign / optimisation of the temporary bypass through the planning of a ‘retaining dam’ sheet pile wall