Unbundling Barchembach Essen

  • Specialised civil engineering
  • Eiffage Infra-Spezialtiefbau

Kund

Entwässerung Essen GmbH

Projektvolym

3.8 million EUR

Byggtid

7 months

Railway crossings from a triple press pit with different nominal diameters

  • Pneumatic tunnelling with open bonnet blade
  • Roadheader excavator and scrapers
  • Dry conveying
  • Compressed air up to 0.7 bar
  • Triple press pit DN 2200, DN 1800, DN 1600
  • Crossing German railway, tram, roads
  • DN 1600 section with S-curve and R = 200 m
  • Own sluice system DN 1800
  • Conversion of DN 2200 sluice system to DA 2800