Sleeper and track renewal Eilenburg-Jesewitz

  • Track and railway construction
  • Eiffage Infra-Rail

Kund

DB Netz AG, Leipzig

Projektvolym

1 million EUR

Byggtid

November to December 2012; load tap May 2013

6.6 km of track and sleeper replacement with the P100 renewal train, ballast cleaning and full ballast renewal

Sleeper and track renewal using the assembly line method from kilometre 22.662 to kilometre 16.016

 

Superstructure/civil engineering:

  • Sleeper replacement with P100 track renewal train (6,646 m of track)
  • Subsequent ballast cleaning (5,796 m)
  • Full ballast renewal (850 m, of which 600 m PSS installation)
  • Rail replacement (1,015 m)

Related services:

  • Construction of edge paths (4,433 m)
  • Side drainage (540 m)
  • Reprofiling of railway trenches (1,520 m)
  • Dismantling and renewal of two level crossings