Sleeper and track renewal using the assembly line method from kilometre 22.662 to kilometre 16.016
Superstructure/civil engineering:
- Sleeper replacement with P100 track renewal train (6,646 m of track)
- Subsequent ballast cleaning (5,796 m)
- Full ballast renewal (850 m, of which 600 m PSS installation)
- Rail replacement (1,015 m)
Related services:
- Construction of edge paths (4,433 m)
- Side drainage (540 m)
- Reprofiling of railway trenches (1,520 m)
- Dismantling and renewal of two level crossings