The route is located in a structurally weak region and is of great importance for connecting the people living there to the capital Berlin. The project started back in April with a comprehensive explosive ordnance survey over a length of 7 kilometres. The entire construction site extended over 11 km in the area between Müncheberg and Rehfelde.
In this area, Eiffage Infra-Rail undertook the complete sleeper replacement, renewed three level crossings and completed the 11 km section of track with a new side track. Eiffage Infra-Rail thus ensured a sustainable renewal of the track systems. The time had finally come in August: the completely renovated section of track was opened for further use as planned. A great success for the entire team and an important contribution to strengthening the region!