Photo shoot in Mörlenbach

  • Structural engineering
  • Road and traffic route construction
  • Civil engineering
  • Tunnelling technology
  • Eiffage Infra-Süd
  • Project update
  • Company news

Nobodycan get past these guys here😎, except for our project manager and, on this day, perhaps the photographer🤩.

Because a photo shoot took place at our construction sites in Mörlenbach, the Berkersklamm tunnel and Kisselhöhe tunnel, on 14 August 2025. A similar shoot had already taken place at our construction site in Landshut at the Isar Bridge in spring. And now it was off from the beautiful waters into the deep underground🙃.

On the hottest day of 2025, not only were these strong guys photographed, but impressive construction progress was also recorded💪:

At the Berkersklamm tunnel , tunnelling in the bench and floor area is in full swing. At the same time, complex structural engineering constructions are being built on the tunnel aprons, as can be clearly seen in the following pictures of the retaining walls and trough structures. The material excavated from the tunnel is quickly removed and immediately reinstalled behind the structural engineering constructions genutzt🏗️.

Meanwhile, work is being carried out on the north and south pre-cuts of the Kisselhöhe tunnel. This includes extensive earthworks including slope stabilisation and asphalting of the construction road to enable safe and efficient transport. The ramp filling for the crown drive is also underway and the final steps for the tunnel opening ceremony on 26 August 2025 are in full swing (we reported🎉).

THANK YOU to everyone for this great shoot and the brilliant photos! We will live on these for a long time👏.

We wish everyone involved continued success and an accident-free construction period. Good luck!