Dülmen southern bypass

  • Structural engineering
  • Eiffage Infra-West

Client

Deutsche Bahn Netz AG, Hamm

Project volume

1.36 million EUR

Construction time

October 2015 - September 2016

Construction of a new railway overpass at Dernekämper Höhenweg on the line between Dülmen and Sythen

Work under partial and full closure
Full closure for bridge insertion (04 - 09 May)2016)
Removal of the track yokes and superstructure
Shoring the superstructure
Installation of transverse shoring to secure the pylon
Back anchoring of the transverse shoring
Creation of the excavation pit, shunting track
Insertion of the frame weighing more than 2500 tonnes over a distance of 45 m
Backfilling of the frame
Removal of shoring and anchoring
Restore superstructure and tracks
Removal of auxiliary cable bridges and cable relocation in cable duct Final position