Work under partial and full closure
Full closure for bridge insertion (04 - 09 May)2016)
Removal of the track yokes and superstructure
Shoring the superstructure
Installation of transverse shoring to secure the pylon
Back anchoring of the transverse shoring
Creation of the excavation pit, shunting track
Insertion of the frame weighing more than 2500 tonnes over a distance of 45 m
Backfilling of the frame
Removal of shoring and anchoring
Restore superstructure and tracks
Removal of auxiliary cable bridges and cable relocation in cable duct Final position
Dülmen southern bypass
- Structural engineering
- Eiffage Infra-West