Nuremberg bypass MDK

  • Structural engineering
  • Road and traffic route construction
  • Civil engineering
  • Eiffage Infra-Süd
  • Project update

Client

Stadt Nürnberg

Project volume

EUR 10 million net

Construction time

New construction: 03/2025 - 03/2026, demolition 05/2030 - 11/2030

Nuremberg, construction of the temporary bypass for the replacement of the bridges over the Main-Danube Canal and the south-west bypass

  • 700 m temporary bypass
  • 40,000 m³ earth masses of soldier pile wall shoring
  • 105 m solid retaining wall
  • 10,000 m² asphalt surfaces
  • 1,000 m concrete drainage pipes

 

Rescheduling / optimisation of the temporary bypass by planning a soldier pile wall shoring "cofferdam"