Final stop: Sperrpause – all aboard, please!

  • Track and railway construction
  • Road and traffic route construction
  • Civil engineering
  • Eiffage Infra-Süd
  • Project update
  • Company news

Since Monday 14 September 26, train services have resumed at our construction site in Hersbruck. Following the end of the closure period and the test and load-testing runs over the weekend , all signals were green, meaning the line could be opened to rail traffic on schedule.

It was a frantic rush for our project team right up to the last minute , and everyone gave their all to achieve this goal together . This collective effort knew no bounds, as every possible resource was mobilised, even beyond the Bavarian border . The tamping machine from our sister company, Eiffage Infra-Rail GmbH, carried out precise work on the final day of the closure. For any of us who aren’t track builders: what exactly is a tamping machine? A tamping machine is used in track construction to correct or level the position and stability of the track:

  • It lifts the track slightly,
  • aligns it to the correct height and lateral position,
  • compacts the ballast beneath the sleepers using so-called tamping picks,
  • thereby creating an even and load-bearing base for the sleepers that can withstand the enormous loads of the trains.

The highlights of the track closure were captured in two photo shoots, including the installation of a time-lapse camera – powered by Richard Vogel from Baumedien. We had a little taster two weeks ago, but now that the work is done , the satisfaction is all the greater – and @ dear project team, you can and absolutely must be proud of yourselves, because we certainly are.