The access road in the Rhein-Lippe-Hafen-Nord area, including the supply and disposal lines, was laid over a length of approx. 670 metres.
DeltaPort GmbH & Co KG (operator of the Rhein-Lippe-Hafen-Nord harbour) intended to change the division of the property due to a planned settlement in the Rhein-Lippe-Hafen-Nord area in Wesel. This required the relocation of the access road and the existing supply and disposal lines in the original route. The road was approx. 670 metres long.
In addition, a new DN 2000 rainwater retention sewer was built, including the demolition of the existing DN 1600/2000 sewer.
The missing surface course (asphalt concrete) is to be applied in autumn 2023.