Herrenstraße level crossing (length approx. 9 m, clear width 6 m)
Ground reinforcement using HDI
Production of reinforced concrete half frame in FT construction method, 7 parts substructures + 2 caps in field factory
Production of an auxiliary cable bridge for railway cables
Total closure of line 3010 Koblenz-Perl from 27.10.2017 to 02.11.2017
Dismantling track systems and securing overhead line mast
Demolition of existing structure and construction of excavation pits
Lifting in the prefabricated parts and applying internal prestressing
Backfilling the excavation pits, restoring the tracks incl. LST work
St. Georgstraße level crossing (length approx. 18 m, clear width 3 m)
Production of reinforced concrete half frame and wing extension in FT construction method,
12 parts of substructures + 1 cap in field factory
Production of an auxiliary cable bridge for railway cables
Total closure of line 3010 Koblenz-Perl from 27.10.2017 to 02.11.2017
Dismantling track systems incl. 2 points
Demolition of existing structure and construction of excavation pits
Lifting in the prefabricated parts and applying internal prestressing
Backfilling the excavation pits, restoring the tracks incl. LST work