EÜ Distelner Straße in Herten

  • Structural engineering
  • Eiffage Infra-West

Client

Deutsche Bahn Netz AG, Duisburg

Project volume

2.4 million EUR

Construction time

February 2018 - June 2018

New construction of the railway overpass over Distelner Straße in Herten

New railway overpass
- Clear width of 6.00 m 
- Clear height of >= 4.25 m
- Production of reinforced concrete half frame in FT construction method,
4 parts substructures + 2 caps and 2 foundation beams in field factory

Construction of an auxiliary cable bridge for railway cables
Total closure of the line, line 2250
Dismantling
Demolition of existing structure and construction of the excavation pits
Lifting of the prefabricated parts and application of internal prestressing
Backfilling of the excavation pits, restoration of the tracks incl. LST work