This included the following services:
- 10,500 tonnes of soil, old gravel and rubble removed and disposed of
- 900 tonnes of soil removed and reinstalled
- 2,420 tonnes of PSS delivered and installed
- 300 metres of deep drainage supplied and installed
- 235 m of track removed
- 900 m of track installed
- 4 points supplied and installed
- 1,050 m of rail supplied
- 770 sleepers supplied
- 3,070 tonnes of ballast supplied
- 7 pcs. Lighting units with masts supplied and installed
- 7 pile-driven pipe foundations produced