In the course of this, the centre track was dismantled and the platform and access structures were built. A new track including embankment widening, construction of a retaining wall, wing walls and abutments were built.
The stop was connected with underground cable laying work and signalling technology.
This included the following services:
- Civil engineering with construction of abutments, access structure, support system for stairs
- Heavy earthworks with construction of embankment widening, excavation pit excavation, soil replacement
- Track construction
- Cable civil engineering
- Specialised civil engineering with construction of retaining wall (160 m), bored pile work
- Platform construction
- Platform equipment
- Steel construction work with stairs, renewal of railway overpass (bridge)