We already widened the carriageway in the direction of Berlin in 2022. This was followed in 2023 by the resurfacing of the carriageway in the opposite direction, which we have now successfully completed.
In total, approx. 84,500 to. of asphalt milled, 64,500 m³ of concrete carriageway and 13,400 m³ of verges constructed.