Nordlandsbanen 2019-2021

  • Track and railway construction
  • Eiffage Infra-Nordic

Auftraggeber

NRC Group

Projektvolumen

100 000 000 SEK

Bauzeit

2019-08 - 2021-08

  • 71 km track renewal over the course of 3 years.
  • Value: 100 000 000 SEK
  • Duration: 2019-08 – 2021-09
  • Track upgraded to concrete sleepers with Fastclip.
  • Track alignment and ballast profiling included.