Work carried out:
- 350 m centre drainage in the Villa Hügel platform area
- 250 m platform removed, driven off and disposed of
- 2 x 450 m of track removed for soil probing and grouting
- Replacement of ballast and installation of a PSS along the entire construction length
- Supply and disposal of all required substances and materials
- 2,000 m of mechanical ballast cleaning (RM80 and 6 x MFS 100)
- 5,400 m rail replacement
- Welding work carried out in-house using the AT method
- Mechanical tamping work
- Conventional removal of various sludge spots
- 1,500 m construction of railway side ditches
- 250 single sleeper replacements
- 400 m of ballast retaining plates installed