TU Chemnitz new construction 3 field sports hall - bored pile foundation

  • Civil engineering
  • Eiffage Infra-Ost

Client

Staatsbetrieb Sächsisches Immobilien -und Baumanagement NL Chemnitz

Project volume

0.5 million EUR

Construction time

3 months

This new sports hall and associated institute building will be located at the heart of the Chemnitz University of Technology campus.

The bidding consortium Eiffage Infra-Ost with Eiffage Infra Spezialtiefbau was awarded the contract for the foundation of a new sports hall at Chemnitz University of Technology in July 2021.
eiffage Infra Ost and Eiffage Infra Spezialtiefbau are building the bored pile foundation for the structure.

In the approx. 4000 m² excavation pit, approx. 13,000 tonnes of RC material was first installed to fill the excavation pit. The drilling level was then prepared for the special foundation engineering.
The foundation of the building shell consists of pile cap beams, which stand on 170 bored piles. Due to the tight schedule, the latter were completed using the VdW method with a turnaround time of up to 20 minutes.

The complete foundation of the sports hall was completed in around 8 weeks.