Signalling boom in Bad Krozingen

  • Structural engineering
  • Eiffage Infra-West

Client

DB Netz AG, Bad Krozingen

Project volume

0.68 million EUR

Construction time

3 months

New construction of 3 signalling booms

  • Cut back 1,200 m² of green areas/shrubbery
  • 3.420 tonnes of backfill
    Construction of temporary ramps and standing areas for the large drilling rig for
    Construction of large bored piles up to 8 m deep and 1.50 m in diameter
  • Installation of 3 signalling booms