Sewer renewal Castroper Straße in Datteln, 4th construction phase

  • Civil engineering
  • Eiffage Infra-West

Client

Stadt Datteln

Project volume

3.0 million EUR

Construction time

February 2017 - September 2019

Renewal of an existing combined sewerage system and a drainage channel to be laid parallel to it in Castroper Straße in Datteln over a total length of around 871 metres.

Construction sections no. 1 - 8 and additional work

  • 250 m sewer DN 900 B
  • 150 m sewer DN 800 B
  • 355 m sewer DN 700 B
  • 90 m sewer DN 600 B
  • 113 m DN 600 - 300 PVC-U
  • 735 m drainage pipes DN 250
  • Prefabricated manhole structures and special manhole structures
  • Drainage
  • Shoring work
  • Inliner rehabilitation
  • Road demolition, ground works, disposal
  • Road reconstruction (road construction, paving, kerbs, asphalt)
  • HDI injection process