A) "Beckumer Straße" thoroughfare
The asphalt surface course and binder course are to be renewed here in two subsections under full closure. To be carried out during the 2016 summer holidays.
B) "Warendorfer Straße" thoroughfare
The asphalt surface course and binder course in the area in front of a large traffic light junction is to be renewed here under partial closure, divided into 3 strips. Execution during the 2016 summer holidays.
C) B 58 Ahlen towards Drensteinfurt (out of town)
The "bridge structure over the Richterbach" is to be renovated here.
In addition, the asphalt surface course and binder course will be renewed in 4 construction phases. The carriageway cross-section will be reduced from 12 m to 8 m in favour of a new cycle path (mainly located on the north side). In addition, a crossing aid will be installed at the start and end of the construction work and two new bus bays with bus bollards and a bus shelter will be created.
Key data
- Construction of 18,300 m² asphalt binder course
- 18,300 m² asphalt surface course
- 5,420 m² asphalt base course
- Install 770 m³ frost protection layer
- 1,500 m³ topsoil movement
- Milling 19,090 m² of asphalt
- Take up 340 m³ asphalt pavement
- Lay 75 m of pipework