Replacement of Sudbachtal bridge

  • Structural engineering
  • Eiffage Infra-West

Client

Landesbetrieb Straßen.NRW

Project volume

4.1 million net EUR

Construction time

09/2017 - 02/2020

Demolition and replacement construction of the bridge over the Sudbachtal in the course of the new B 611 from Gohfeld to Löhne

Prestressed 3-span reinforced concrete bridge

Superstructure:
Longitudinally prestressed five-span prestressed concrete slab beams supplied as prestressed precast elements and installed with continuity tendons.
Production of the in-situ concrete addition to the carriageway slab as well as end and cross girders

Spans of 30.5 m - 38.0 m - 30.5 m
Clear width: 99 m

Blasting and thus demolition of the existing bridge