Mainzelbahn TA 5

  • Track and railway construction
  • Eiffage Infra-Rail
  • Eiffage Infra-Südwest

Client

Mainzer Verkehrsges. mbH

Project volume

9.8 million EUR (total volume) 2.5 million EUR (track construction volume)

Construction time

06/2014 - 07/2016

Extension of the tramway network from Mainz main station to Lerchenberg. Mainz to Lerchenberg

5,400 m total length, of which

  • 960 m grooved track
  • 4,330 m vignole rail track
  • 11,000 tonnes of track ballast
  • 7,000 sleepers
  • 1,000m3 concrete
  • 700 pieces of welding
  • 13,000m2 turf covering
  • 2 pcs. Switches