Renewal of the double-track line 6153 between km 13.58 Köpenick and km 23.00 (9.42 km) Erkner to increase the travelling speed as well as the axle load parallel to the existing double-track S-Bahn line including substructure, track construction, structural engineering and equipment under railway operation in closed intervals.
- New construction of 3 railway overpasses during railway operations
- Renewal of 2 pedestrian subways in the listed surroundings
- Adaptation work on the station access areas in the listed surroundings
- approx. 3,900 m of noise barrier work
- approx. 19,580 m track removal
- approx. 18,570 m new track construction
- approx. 410,000 tonnes of demolition materials and disposal
- approx. 48,000 tonnes of PSS
- approx. 13,000 m cable duct
- approx. 35,480 m of track work
- approx. 1,540 m of conductor rail work in the suburban railway area