Hünxer Heide wind turbines

  • Civil engineering
  • Eiffage Infra-West

Client

Windpark Hünxer Heide GmbH Essen

Project volume

1.15 million EUR

Construction time

November 2017 - August 2018

Execution of ground works for the construction of four wind turbines in the Hünxer Heide, between the Bergschlagweg road in the south and the "Lanter" road in the north.

  • Remove 5,200 m³ topsoil, load, place on windrow
  • Deliver and install 7,500 m³ HKS 0/45 ballast base course
  • 5,530 m³ Delivery and installation of a BaseLith 0/45 base course
  • 2,100 m³ Delivery and installation of a HKS 0/45 ballast base layer as a cushioning layer
  • 10,900 m³ of backfill and soils removed, loaded, transported, piled up and partially reinstalled
     
  • 15,000 tonnes of backfill and soil removed, loaded and disposed of, Z 0 + Z 1.2
  • Supply and install 1,450 m cable conduit OD 160 mm
  • Supply 740 m empty conduit for fibre optic cable and lay on sand bed