Hattingen central landfill site

  • Civil engineering
  • Eiffage Infra-West

Client

AGR mbH

Project volume

1.5 million EUR

Construction time

June 2013 - December 2014

Profiling and development work as well as sealing construction

  • 55,000 m² terrain profiling
  • 25,000 m² site clearance, profiling of the area
  • 24,000 m³ backfill, material provided by customer
  • 13,500 m³ base course, material provided by customer
  • 25,000 m² subgrade for mineral sealing
  • Supply and install 43,500 m² geotextile
  • Produce 14,000 m³ mineral sealing
  • Produce 9,000 m³ surface drainage 16/32
  • 20,000 m³ of soil for the lower recultivation layer
  • 25,000 m³ of soil for the upper recultivation layer
  • 25,000 m³ compost for the recultivation layer
  • Landfill gas engineering measures