GE/GEoS Hockeroda - Probstzella

  • Track and railway construction
  • Eiffage Infra-Rail

Client

DB Netz AG Leipzig

Project volume

3.5 million EUR

Construction time

14.07.2016 - 03.09.2016

12,701 m track renewal with ballast cleaning using the assembly line method

Superstructure/civil engineering:

  • 12,701 m track renewal using the assembly line method with ballast cleaning/bed preparation
  • Renewal of three culverts and two double-track level crossings

Related services:

  • Clean and flush 8,400 m of deep drainage;
  • construct 12,700 m of verge paths;
  • 165 m of edge path shoring