Installation of 4 auxiliary bridges ZH 26
Core construction period: total closure from 09.10.2020 to 25.10.2020
- Working levels and ramps
- Construction of auxiliary bridge foundations
- 16 pcs cased borehole DN 120 cm, 25 m depth
- 17 m reinforcement cages, 13 m HEB 700 plug-in beams
- approx. 2,500 m³ excavation pit excavation
- Dismantling of the 4 existing superstructures
- Partial demolition of existing abutments
- Construction of 8 auxiliary bridge supports + shoring infill made of steel sheets
- Excavation and lowering into final position of 4 auxiliary bridges ZH 26, 26.40 m span + longitudinal bracing
- Backfilling of excavation pit
- Superstructure