Core construction period in two closures (2 weeks Easter 2018) and (11 weeks summer 2018)
Superstructure as single-span girder with single-track truss superstructure
- Span width of 55 m
- Width & height 8 m each
- 400 tonnes dead weight
- Construction of the bridge structure incl. substructures and foundations
- Technical demolition of the old superstructure with a temporary foundation in the Agger river
- Transport of superstructure using SPMTs
- Foundations for a skidding structure in the Agger
- Cable civil engineering and track construction work
- TC systems & landscaping