On behalf of Straßen NRW, our road construction team is redesigning the cross-section of the L856, which means that the asphalt surface is being repaired.
The construction site extends over 3.2 km and is being worked on in 7 sections.
This second section is an island construction site, with traffic passing to the left and right of the work area.
- The existing asphalt surface will be milled off (approx. 44,000 m²).
- An additional frost protection layer of recycled material will then be laid (approx. 18,000 tonnes).
- A 24 cm thick layer of new asphalt is applied (approx. 21,000 tonnes).
- Paving and kerbstone work
- Traffic signs/road signs