Bridge over the Weißeritzmühlgraben

  • Civil engineering
  • Structural engineering
  • Eiffage Infra-Ost

Client

Straßen- und Tiefbauamt Landeshauptstadt Dresden

Project volume

182,420.00 EUR

Construction time

March 2018 - May 2018 March 2019 - May 2019

The planned construction project involved restoring the load-bearing capacity of the Weißeritzmühlgraben ditch vault in the Ostra-Allee area of Dresden.

The vault of the Weißeritzmühlgraben was built around 1906 and used as a watercourse to supply water power to various mills located along its course.

Eiffage Infra-Ost GmbH opened up the vault in several places, bricked up the start and end areas of the construction sections and then backfilled the ditch with 1,150m3 of liquid soil. Various masonry and sealing work was also carried out.