The resurfacing was carried out over a length of 5.3 km and covered the entire width of the carriageway, including the rehabilitation of the 4 cm surface course and 8 cm binder course as well as part of the asphalt base course. In the area of the structures, the surface course was rehabilitated while retaining the protective layer.
In areas of cracking, reinforcement mesh was laid on the asphalt base course.
Immediately after the surface course was paved, the centre markings were produced as permanent markings in foil.
To reinforce the diversion routes for the full closure of the B174, the edge of the carriageway and the asphalt binder and surface course were renewed in places in the area of the S 216 state road from Reitzenhain to Rübenau and on the B171 Hüttengrund, as well as across the full width of the carriageway.
B 174 carriageway renewal