ARGE turning facility Bernsdorf - CVAG

  • Road and traffic route construction
  • Civil engineering
  • Eiffage Infra-Ost

Client

Chemnitzer Verkehrs-AG (CVAG)

Project volume

1.175 million EUR

Construction time

6 months

In June 2020, Chemnitzer Verkehrs-AG commissioned the barrier-free expansion of the public transport stops in the area of the turning area in the Bernsdorf district of Chemnitz.

The object of the contract is the fundamental renewal of the inner track loop as well as the expansion of the arrival stop for trams and the departure stop for buses. The carriageway on the bus access road from Bernsdorfer Straße will be adapted. In addition, an emergency stop will be built in the area of the departure stop for trams for the inner track.
Eiffage Infra-Ost is carrying out the work as a consortium with Rhomberg Sersa Deutschland GmbH.

The type and scope of the road construction work includes the following main services:

- Demolition of the existing carriageway areas in the construction area
- Dismantling of the track systems
- Basic track and carriageway construction
- Barrier-free expansion of the stops
- Construction of temporary temporary structures for pedestrian guidance

 

Update : 30 November 2020

The work to be carried out has been completed. The green areas are currently being created and the temporary pedestrian routes and stops are being dismantled.