- Break up approx. 40,000 m² of road surface (concrete/asphalt)
- Produce approx. 17,000 m³ of earth concrete edge beams
- approx. 29,000 m² consolidation work
- Approx. 650 m² concrete repair work
- Replace 4 carriageway transition structures
- approx. 5,200 m² sealing work
- Paving approx. 29,000 m² of asphalt
- Paving approx. 40,000 m² of mastic asphalt
Special feature: Contractual penalty of € 15,000.00/KT in the event of construction delays