Project update RAG - Reorganisation of central water drainage Haus Aden, 1st construction phase

  • Civil engineering
  • Eiffage Infra-Nordwest

An important milestone has been reached!

Following the successful completion of the DN 2800 and DN 3200 pipe jacking under the Datteln-Hamm Canal at the end of 2023, work continued at full speed:

  • Equipping the media channels with flood pipes (DN 1000 & DN 500 steel) and mine water pipes (DN 600 & DN 400 GGG)
  • Construction of the 50 cm thick reinforced concrete inner shells in the start and target shafts
  • Assembly work on the steel structure in the target shaft

 

Next steps:

  • Installation of the risers for high and pit water
  • Connection to the underground area
  • Same procedure in the start shaft

 

We will keep you up to date!